Siding & roofing
Closing a building in: sheathing and wrap on the walls, siding over them, decking and roofing on the rafters. Each step here is one of a guide’s, built by HausCrafter.
8 × 8 ft shed with a shed roof, step 5
Sheathe, wrap and side the walls

- Nail the sheathing to the studs in 4 × 8 ft sheets, standing up, each edge on a stud, and cut round the doors’ opening. The pieces below are what the sheets are cut to.
- Staple the house wrap over it, each course lapping the one under it, and hang the siding over the wrap from the bottom up.
| Piece | How much |
|---|---|
| siding | 6 pieces |
| house wrap | 6 pieces |
| sheathing | 16 pieces |
| gable sheathing | 3 pieces |
| gable cladding | 3 pieces |
8 × 8 ft shed with a shed roof, step 6
Deck and roof it

- Nail the roof decking across the rafters, its joints staggered, and the fascia over the sub-fascia and barge rafters.
- At 3 in 12, a shingle roof wants a double layer of underlayment under it. Your shingles’ maker says the least pitch they are good for, and what they ask under them.
- Shingle from the low eave up, each course lapping the one under it.
| Piece | How much |
|---|---|
| roof decking | 31 pieces |
| fascia | 4 pieces |
| soffit | 4 pieces |
| shingles | 0.83 squares |
Building along? Ask about a step in Discussion, and when yours stands, show it in Builds and projects.